Friday, August 19, 2011

151 Main Street Project Update - Week of Aug. 22nd (City of Sun Prairie Engineering Department)

The following activities are scheduled for the week of August 22nd:

Work performed next week will consist of finishing miscellaneous items on the North side of Main St and the ramps on the North side. Topsoil placement, seed, fertilize and mulching of the terrace and yards on the north side.

Traffic control will be switching on Thursday August 25th, when all traffic will be shifted to the North side of Main Street. Traffic will be traveling on the new concrete pavement. The traffic will remain one lane in both directions. Turning movement restrictions will remain the same. No left turn from O'Keeffe Ave onto Main Street; no left turns out of Hamilton Place apartments; no left turn onto O'Keeffe Ave from WB traffic.

Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks. People are also strongly encouraged to continue to slow down and watch for construction workers and equipment at all times in the construction zone.

The next business meeting is scheduled for August 25th at 9:00 a.m.

Key Contact Information

City of Sun Prairie Project Office: (608) 215-1167
WisDOT Project Office: (608) 834-1207
Contractor Office (R.G. Huston): (608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail: mainstreet@cityofsunprairie.com