Showing posts with label Interchange. Show all posts
Showing posts with label Interchange. Show all posts
Wednesday, November 9, 2011
151-Main Street Interchange To Open November 14th (City of Sun Prairie Engineering Department)
151-Main Street Interchange To Open November 14th - Final Update
Here is the final project update on the 151-Main Street Interchange project:
With weather conditions over the past couple days slowing the work onsite and efforts that are still needed to get the signals into operation, the project team is planning to have the signals ready to operate on Monday November 14th in conjunction with opening the roadway. This should allow time to finish the cabinet wiring, signs, pavement marking and other miscellaneous items on the site.
Blogger's Note: And there was much rejoicing!
Labels:
Construction,
Day 313,
Interchange,
Main Street,
Post 1,
Project 365,
Sun Prairie,
U.S. 151,
Wisconsin
Saturday, October 29, 2011
151 Main Street Project Update Week of October 31st, 2011 (City of Sun Prairie Engineering Department)
Here is the schedule for the week of Oct. 31st on the 151-Main Street Interchange project:
- Traffic switch to occur on Monday, traffic to travel on outside lanes along Main Street (Originally scheduled for Oct. 26th)
- Concrete placed in TWLTL (two way left turn lane).
- Median work will continue.
- Landscaping and restoration will continue.
- Next Thursday Nov. 3rd at 9:00 a.m. will be the last business meeting held for this project.
Truck Traffic Advisory:
It is currently very
difficult for large trucks to make a left turn onto Main Street from the
SB 151 ramp. These trucks may want to either 1) turn right and go
around the Round-a-bout to go east bound on Main
Street, or 2) they could go up to the 151-CTH C - Reiner Rd interchange
and turn around to head NB on 151and exit on to Main Street. This right
turn is much easier for large trucks.
Note that there are no turns onto Main Street from O'Keeffe Ave.
Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks.
People are also strongly encouraged to continue to slow
down and watch for construction workers and equipment at all times in
the construction zone.
In addition, vehicles traveling
westbound on W. Main Street. and wanting to access businesses along
O'Keeffe Avenue must turn at the Clarmar Drive intersection. Access to
O'Keeffe Avenue for westbound vehicles does
not exist west of Clarmar Drive.
Key Contact Information
City of Sun Prairie Project Office: (608) 215-1167
WisDOT Project Office: (608) 834-1207
Contractor Office (R.G. Huston): (608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail:
mainstreet@cityofsunprairie.com
Labels:
Construction,
Day 302,
Interchange,
Main Street,
Post 1,
Project 365,
Sun Prairie,
U.S. 151,
Wisconsin
Sunday, October 23, 2011
151 Main Street Interchange Project Update - Week of Oct. 24th (City of Sun Prairie Engineering Department)
Here is the schedule for the week of Oct. 24th on the 151-Main Street Interchange project:
- Place sidewalks and concrete gaps on Monday and Tuesday.
- Switch Main Street traffic to the outside lanes on Wednesday, beginning of the final phase.
- Pour the TWLTL and medians on Thursday and Friday.
- Possible striping on Thursday and Friday.
Truck Traffic Advisory:
It is currently very
difficult for large trucks to make a left turn onto Main Street from the
SB 151 ramp. These trucks may want to either 1) turn right and go
around the Round-a-bout to go east bound on Main
Street, or 2) they could go up to the 151-CTH C - Reiner Rd interchange
and turn around to head NB on 151and exit on to Main Street. This right
turn is much easier for large trucks.
Note that there are no turns onto Main Street from O'Keeffe Ave.
Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks.
People are also strongly encouraged to continue to slow
down and watch for construction workers and equipment at all times in
the construction zone.
In addition, vehicles traveling
westbound on W. Main Street. and wanting to access businesses along
O'Keeffe Avenue must turn at the Clarmar Drive intersection. Access to
O'Keeffe Avenue for westbound vehicles does
not exist west of Clarmar Drive.
Key Contact Information
City of Sun Prairie Project Office: (608) 215-1167
WisDOT Project Office: (608) 834-1207
Contractor Office (R.G. Huston): (608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail:
mainstreet@cityofsunprairie.com
Labels:
Construction,
Day 296,
Interchange,
Main Street,
Post 1,
Project 365,
Sun Prairie,
U.S. 151,
Wisconsin
Friday, July 8, 2011
151 Main Street Project Update - Week of July 11th (City of Sun Prairie Engineering Department)

The following activities are scheduled for the week of July 11th:
Current traffic routes and controls should remain the same through August 4th.
Installation of new watermain will continue on the north side of Main Street.
Storm sewer installation will also be performed early in this week.
The contractor will also be working on construction of a retaining wall underneath the 151 overpass on the north side of Main St.
Grading for the northern lanes of Main St. and the new ramps north of Main St. will be completed, and crushed aggregate base course will be placed.
The northbound on-ramp and the southbound off-ramp will be closed to traffic starting on July 5th, and are scheduled to remain closed through the first week in August. The northbound off ramp from 151 to Main Street and the southbound on ramp from Main Street to 151 will remain open to traffic. Southbound traffic on 151 wanting to get to Main Street will be detoured to use either the STH 19/Windsor St. exit or the CTH C/Reiner Rd. exit. Similarly, Main Street traffic needing to access 151 North will be detoured to the STH 19/Windsor St. exit. Detour signage will be posted before the ramps are closed. In addtion, portable message boards are up and active, and will be updated regularly.
Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks. People are also strongly encouraged to slow down and watch for construction workers and equipment at all times in the construction zone.
Paving of temporary driveways to Hamilton Place off of Hart Rd. and Wal-Mart has been completed.
Temporary signals at the Clarmar Drive / Main Street intersection are operational as are the signals at the ramps east of STH 151. Signals at O'Keeffe have been removed.
Temporary pavement for lane shifts has been completed for this phase of the project.
The next business meeting is scheduled for July 14th at 9:00 a.m.
Key Contact Information
City of Sun Prairie Project Office: (608) 215-1167
WisDOT Project Office: (608) 834-1207
Contractor Office (R.G. Huston): (608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail: mainstreet[at]cityofsunprairie.com
Labels:
Construction,
Day 189,
Interchange,
Main Street,
Post 1,
Project 365,
Sun Prairie,
U.S. 151,
Wisconsin
Friday, July 1, 2011
151 Main Street Interchange Project Update - Week of July 4th

Pending Work for Week of July 4th (NEW)
The following activities are scheduled for the week of July 4th:
Traffic will be shifted to the south side of Main Street starting on Tuesday July 5th.
The northbound on-ramp and the southbound off-ramp will be closed to traffic starting on July 5th, and are scheduled to remain closed through the first week in August. The northbound off ramp from 151 to Main Street and the southbound on ramp from Main Street to 151 will remain open to traffic. Southbound traffic on 151 wanting to get to Main Street will be detoured to use either the STH 19/Windsor St. exit or the CTH C/Reiner Rd. exit. Similarly, Main Street traffic needing to access 151 North will be detoured to the STH 19/Windsor St. exit. Detour signage will be posted before the ramps are closed. In addtion, portable message boards are up and active, and will be updated regularly.
Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks.
People are also strongly encouraged to slow down and watch for construction workers and equipment at all times in the construction zone.
Paving of temporary driveways to Hamilton Place off of Hart Rd. and Wal-Mart semi access off O'Keeffe Ave were scheduled to occur the week of June 27th, however weather has delayed these activities until the week of July 4th.
Temporary signals at the Clarmar Drive / Main Street intersection have been erected. This signal will likely become operational during the week of July 4th due to weather delays last week.
Installation of temporary signals at ramps east of STH 151 will continue but will not be made operational at this time.
Temporary pavement continues to be installed to accomodate lane shifts for future phases of construction.
The next business meeting is scheduled for July 14th at 9:00 a.m.
The following activities are scheduled for the week of July 4th:
Traffic will be shifted to the south side of Main Street starting on Tuesday July 5th.
The northbound on-ramp and the southbound off-ramp will be closed to traffic starting on July 5th, and are scheduled to remain closed through the first week in August. The northbound off ramp from 151 to Main Street and the southbound on ramp from Main Street to 151 will remain open to traffic. Southbound traffic on 151 wanting to get to Main Street will be detoured to use either the STH 19/Windsor St. exit or the CTH C/Reiner Rd. exit. Similarly, Main Street traffic needing to access 151 North will be detoured to the STH 19/Windsor St. exit. Detour signage will be posted before the ramps are closed. In addtion, portable message boards are up and active, and will be updated regularly.
Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks.
People are also strongly encouraged to slow down and watch for construction workers and equipment at all times in the construction zone.
Paving of temporary driveways to Hamilton Place off of Hart Rd. and Wal-Mart semi access off O'Keeffe Ave were scheduled to occur the week of June 27th, however weather has delayed these activities until the week of July 4th.
Temporary signals at the Clarmar Drive / Main Street intersection have been erected. This signal will likely become operational during the week of July 4th due to weather delays last week.
Installation of temporary signals at ramps east of STH 151 will continue but will not be made operational at this time.
Temporary pavement continues to be installed to accomodate lane shifts for future phases of construction.
The next business meeting is scheduled for July 14th at 9:00 a.m.
Labels:
Construction,
Day 182,
Interchange,
Main Street,
Post 1,
Project 365,
Sun Prairie,
U.S. 151,
Wisconsin
Friday, June 24, 2011
U.S. 151-Main Street Interchange Project Update for Week of June 27th (City of Sun Prairie Engineering Department)

- Paving of temporary driveways to Hamilton Place off of Hart Rd and Wal-Mart semi access off O'Keeffe Ave should occur the week of June 27th.
- Installation of temporary signals at the Clarmar Drive / Main Street intersection will also continue this week. This signal will likely be operational during this same week.
- Installation of temporary signals at ramps east of STH 151 will continue but will not be made operational at this time.
- The portable message boards will be updated and revised.
- The northbound on-ramp and the southbound off-ramp will not be closed until after July 4th. The other ramps are slated to be open to traffic.
- Temporary pavement will be installed to accommodate lane shifts for future phases of construction.
Key Contact Information:
City of Sun Prairie Project Office: (608) 215-1167
WisDOT Project Office: (608) 834-1207
Contractor Office (R.G. Huston): (608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail: mainstreet@cityofsunprairie.com
Labels:
Construction,
Day 175,
Interchange,
Main Street,
Post 2,
Project 365,
Sun Prairie,
U.S. 151,
Wisconsin
Friday, June 17, 2011
151-Main Street Interchange Project Update for the Week of 6/20/11

http://myemail.constantcontact.com/Welcome-to-the-151-Main-Street-Project-E-Mail-List.html?soid=1105140942393&aid=GpNnQlW6S5I
Blogger's Note: You can now also get these and other Project 365 updates via Facebook and Twitter!
Labels:
Construction,
Day 167,
Interchange,
June 20th,
Main Street,
Post 1,
Project 365,
Sun Prairie,
U.S. 151,
Wisconsin
Subscribe to:
Posts (Atom)