Here is the schedule for the week of Oct. 24th on the 151-Main Street Interchange project:
- Place sidewalks and concrete gaps on Monday and Tuesday.
- Switch Main Street traffic to the outside lanes on Wednesday, beginning of the final phase.
- Pour the TWLTL and medians on Thursday and Friday.
- Possible striping on Thursday and Friday.
Truck Traffic Advisory:
It is currently very
difficult for large trucks to make a left turn onto Main Street from the
SB 151 ramp. These trucks may want to either 1) turn right and go
around the Round-a-bout to go east bound on Main
Street, or 2) they could go up to the 151-CTH C - Reiner Rd interchange
and turn around to head NB on 151and exit on to Main Street. This right
turn is much easier for large trucks.
Note that there are no turns onto Main Street from O'Keeffe Ave.
Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks.
People are also strongly encouraged to continue to slow
down and watch for construction workers and equipment at all times in
the construction zone.
In addition, vehicles traveling
westbound on W. Main Street. and wanting to access businesses along
O'Keeffe Avenue must turn at the Clarmar Drive intersection. Access to
O'Keeffe Avenue for westbound vehicles does
not exist west of Clarmar Drive.
Key Contact Information
City of Sun Prairie Project Office: (608) 215-1167
WisDOT Project Office: (608) 834-1207
Contractor Office (R.G. Huston): (608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail:
mainstreet@cityofsunprairie.com
No comments:
Post a Comment