151 Main Street Project Update for the Week of July 18th (City of Sun Prairie Engineering Department)

Project Status: On Schedule

The following activities are scheduled for the week of July 18th:


Grading operations are scheduled to be completed on the north side of Main Street this coming week.

Conduit crossings for street lighting and traffic signals will be installed.

Concrete for the westbound driving lanes will be poured this coming week.

No changes in traffic control is anticipated at this time.

The northbound on-ramp and the southbound off-ramp will be closed to traffic through the first week in August. The northbound off ramp from 151 to Main Street and the southbound on ramp from Main Street to 151 will remain open to traffic. Southbound traffic on 151 wanting to get to Main Street will be detoured to use either the STH 19/Windsor St. exit or the CTH C/Reiner Rd. exit. Similarly, Main Street traffic needing to access 151 North will be detoured to the STH 19/Windsor St. exit. Detour signage will be posted before the ramps are closed. In addtion, portable message boards are up and active, and will be updated regularly.

Persons travelling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks. People are also strongly encouraged to slow down and watch for construction workers and equipment at all times in the construction zone.

The next business meeting is scheduled for July 28th at 9:00 a.m.

Key Contact Information

City of Sun Prairie Project Office: (608) 215-1167
WisDOT Project Office: (608) 834-1207
Contractor Office (R.G. Huston): (608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail: mainstreet@cityofsunprairie.com

No comments: