The contractor anticipates paving underneath the overpass this weekend.
Depending upon weather, the opening of the northbound on ramp open maybe delayed. (Originally scheduled for opening on Aug. 5th)
Crosswalks and bike lanes in the area of the ramps is likely to remain closed for another week or so, as the contractor finishes up curbing in these areas.
Overall, the Nov. 4 target completion date is still the goal.
Drivers should watch for minor shifts in traffic control in the area of the ramps while they are completed.
Persons traveling this route are advised that construction is likely to be occurring on Saturdays for the next several weeks.
People are also strongly encouraged to slow down and watch for construction workers and equipment at all times in the construction zone.
The next business meeting is scheduled for Aug. 11 at 9 a.m.
Key Contact Information:
City of Sun Prairie Project Office:(608) 215-1167
WisDOT Project Office: 608) 834-1207
Contractor Office (R.G. Huston):608) 255-9223
Project Office Address: 1632 W. Main St. (Access from Hart Rd.)
E-mail: mainstreet@cityofsunprairie.com
No comments:
Post a Comment